Denver Terminal to Elati Transmission Project

Home > Denver Terminal to Elati Transmission Project

Overview

We are replacing and upgrading approximately 1.5 miles of the 230-kilovolt electric transmission line between the existing Denver Terminal Substation (West 14th Avenue and Zuni Street) and the Elati Substation (West 13th Avenue and Elati Street) in Denver, Colorado. Most replacements will be underground (1.26 miles), with 0.21 miles of overhead line upgrades.

This project is part of the larger Denver Metro Transmission Upgrades to upgrade the existing electric system to support new power generation sources and meet future electricity needs.

This map is a graphic and may not show exact locations 

Schedule

Work is expected to occur between October 2030 and April 2031.

Schedules are subject to change. 